| |
|
| |
| |
The
following process outlines a typical set of
'architectural work stages' that we would
likely work through with a client for any
building or architectural project.
For
further information, or for a more specific
explanation of the process, please feel free
to contact us. |
|
|
|
| |
Work
Stage A and B: Inception and Feasibility |
| 1.1. |
Discuss
the clients' requirements; assess these and
give general advice on how to proceed. |
| 1.2. |
Advise on
any need for the appointment of other professional
consultants, specialist contractors, sub-contractors
or suppliers. |
| 1.3. |
Carry
out such preparatory work including dimensional
survey as may be necessary to determine the
client's requirements. |
|
|
| |
|
 |
|
Work
Stage C and D: Outline proposals and Scheme
Design |
| 1.4. |
Prepare
outline proposals and develop a scheme design
based upon your briefing. |
|
|
Make
where required application for planning permission.
Please note the permission itself is beyond
our control and no guarantee can be offered
that it will be granted. |
|
|
|
|
|
|
Work
Stage E: Detail Design |
| 1.6. |
Develop
the scheme design; co-ordinate the design
work of any specialist contractors, sub-contractors
or suppliers. |
| 1.7. |
Advise on
the consequences of any changes on the construction
costs and programme. |
|
|
Make
and negotiate where required applications
for approvals under building acts, regulations
or other statutory requirements. |
|
|
|
|
|
|
Work
Stages F and G : Production Information |
| 1.8. |
Prepare
production information including drawings,
schedules and specification of materials in
sufficient detail to enable a contractor to
prepare a tender. |
| 1.9. |
Prepare electrical layout drawings to indicate
provision of new socket outlets, lighting,
tv aerial outlets etc. |
|
|
|
|
|
|
Work
Stages H, J, K and L : Tender to Completion |
| 1.10. |
Invite tenders
from approved contractors; advise on tenders
submitted or alternatively, arrange for a
price to be negotiated with a contractor. |
| 1.11. |
Advise on
the appointment of a contractor; where required
prepare the building contract and arrange
for it to be signed by the client and contractor. |
| 1.12. |
Administer
the terms of the building contract; visit
the site as appropriate to inspect generally
the progress and quality of the work; make
where required periodic financial reports
to the client. |
| 1.13. |
Administer
the terms of the building contract relating
to the completion of the works; give general
guidance on maintenance; provide a set of
drawings showing the building and the main
lines of drainage. |
|
|
|
|
|
|
Notes.
Under the Construction Design and Management
Regulations 1995 you, as the person instigating
construction works have an obligation to notify
the Health and Safety Executive that works
are to be carried out giving the requisite
period of notice regarding the nature of the
works and the intended start on site dates.
A designers 'risk assessment' will be provided
by KMD for your retention and onward transfer
to your appointed contractor for the works. |
|
|
|
|
|